completion_
2014
client_
private
location_
Frankurt am Main
Bergen-Enkheim
gross floor space_
125 m2
description_
extension of a multifamily house towards the courtyard
service_
stages 1 – 4 kleinundarchitekten
stages 5 – 8 + architekten

In June 2013 we received a call from a friend in need of our professional help. The half finished building wasn’t going to be completed by schedule judging by the slow work pace on the still raw structure. After a while it became clear that even though the construction work had begun in April 2012, only 2 stories had been completed in over 13 months. He wanted to know if it was still possible to complete the project in time for the Christmas Holidays in 2013. We spontaneously accepted the challenge and could complete the project in time for our client to take his first shower in his new home before Christmas. In January 2014 a few small details were completed.